Santy Gold Project

MINERALISATION POTENTIAL

Phase 1 Drilling Completed, Results Imminent 

TENURE AND GEOLOGICAL SETTING

  • 663km2 project area

  • Located in the Tallering Greenstone belt

  • 80% of Project area under cover

PREVIOUS EXPLORATION

  • Phase-1 AC drill program completed, outlining a 2.2km-long gold anomalous zone
  • Chip logging confirmed important geological features, including wide zones of sulphides, comparable to adjacent gold projects within the Santy Gold Project area
  • Encouragingly, with most of the Santy Project under a complex sequence of cover, gold mineralisation was intersected in both weathered and fresh rock
  • Drilling at UM1 intersected anomalous levels of Nickel, Cobalt and Platinum Group Elements (PGE’s), highlighting the potential for Julimar-style ultramafic intrusive mineralisation
First-up exploration focus with high-grade neighbors and 6 prospects

PHASE 2 IN 2022

PLANNED WORK

  • Detailed drone magnetic survey (the IZ5, IZ6, IZ7 & IZ8 prospects)  – January 2022
  • Heritage Survey – Feb 2022
  • Phase 2 AC drilling ~ April 2022
  • (120 AC holes for 5,000m)
  • RC Drilling – Q4 2022